Which term means the relationships where one task must finish before another starts?

World Scholar's Cup Test Prep: Dive into an international competition of knowledge. Practice with flashcards, multiple-choice questions, and comprehensive explanations. Sharpen your skills for success!

Multiple Choice

Which term means the relationships where one task must finish before another starts?

Explanation:
In scheduling, when one task must finish before another can start, that relationship is called a dependency. It creates an order: the first task completes, then the second can begin. This is specifically the finish-to-start type of dependency, which is the typical way we model prerequisites in a plan and helps determine the project timeline and the critical path. The other terms don’t describe this linking rule—the schedule itself is a harmonogram, the Waterfall method is a project process model, and the Stakhanovite Movement is unrelated historically.

In scheduling, when one task must finish before another can start, that relationship is called a dependency. It creates an order: the first task completes, then the second can begin. This is specifically the finish-to-start type of dependency, which is the typical way we model prerequisites in a plan and helps determine the project timeline and the critical path. The other terms don’t describe this linking rule—the schedule itself is a harmonogram, the Waterfall method is a project process model, and the Stakhanovite Movement is unrelated historically.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy